Production for the PCBs are finishing up and they should be at the consolidation warehouse with everything else in the next few days. I'm still waiting for final package sizes from the warehouse so I can shop around for shipping quotes. My goal is to get all the packages picked up by a company from the warehouse sometime before next Friday. The earlier the better in this case. All the other items (cases, plates, small parts) are all there and waiting to ship. I've now gotten a pretty concrete timeline for everything now and have it at the bottom for those that want an idea of when they'll get their boards. Again, if anyone has any questions or concerns, certainly shoot me a PM or email and I'll try my best to get everything sorted out.
March 2 - Restart of PCB assembly
March 9 - Completion of PCB assembly
March 16 - Completion of consolidation and bulk packing
Late March (TBD) - Receive, sort and QC bulk shipment
Late March / Early April (TBD) - Pack and ship to customers
Mid / Late April (TBD) - Finish orders requiring assembly
I've also ordered and received all the packaging needed for the GB. It's taking up a ton of space in the garage. There are something like 300 boxes and 1000 feet of bubble wrap in that picture. As soon as everything arrives, I'll be ready to ship.