Hey Everyone,
Prototypes have been finished.I should get them very soon!
http://imgur.com/a/tzKv7This brings me to a quick re-outline of our schedule. (Suggestion by binge)
23rd Nov - I recieve the prototype switches and double check to make sure that they are up to standard. On this day I will be sending samples to some community members.
If everything is all good, I will get the switches mass produced, which should only take a few days, then it would be sent out asap. Expect 1st December roughly.
1st-10th December: I will pack up boxes and send them out directly to users in the southern hemisphere and I will send it off to my proxies in the states.
Christmas: You will hopefully revive your switches, granted that the postal services in your area are not overloaded (Sorry no guarantees there
)
Expected Challenges & Things that can go wrongShipping - This shouldn't be too bad, I have now had experience with shipping group buys and honestly its not that bad, just takes time. Now that I have finished my schooling for the year I will have all the time in the world to pack and send.
Prototypes aren't up to standard - Depending on what is wrong with the switch I will request it be fixed, however I presume it will not be that bad or there wont be anything wrong considering that my manufacturer understands the needs of an enthusiast switch.
Let me know if you have any questions