The ALPS GB steps in my mind is  (As the first MX Springs GB in early 2014) -  Hear different opinions - by the end of July
-  Additional Sample production by early Aug
-  Field test by 10+ chosen members by mid Aug      
https://geekhack.org/index.php?topic=55888.msg2239559#msg2239559 -  Set the Final candidates to produce by late Aug   - By Actuation force - 45cN,  50cN,  55cN,  60cN,  65cN,  70cN,  85cN,  100cN,  120cN  etc
-  Open the GB order form for 2-3 weeks, payment to the Proxy
-  Go to the Mass production for 2-3 weeks  (Standard & Gold plated versions)
-  Inspection and pack for 2-3 weeks
-  Ship to the Proxies will take 1 week
-  Ship to Each member - 1 week 